Healthcare / Plumbing VDC & MEP Coordination

NYU Langone Patchogue Ambulatory Surgical Center

How Heleos VDC delivered plumbing design coordination, clash detection, and MEP coordination for the NYU Langone Patchogue Ambulatory Surgical Center — an Article 28 adaptive-reuse healthcare project carved out of a vacant Main Street department store in Patchogue, NY.

Project Facts

Project Overview

Photorealistic exterior rendering of the completed NYU Langone Patchogue Ambulatory Surgical Center, showing the two-story glass-and-metal healthcare facade and NYU Langone Health signage along the Patchogue streetscape.

A vacant Main Street department store became one of Long Island's newest surgical centers — and every pipe had to clear structure and four other trades before a single fitting was cut.

At 196 East Main Street in Patchogue, NYU Langone Health is converting a long-vacant retail building — first the BeeHive, then Mid-Island Department Store, and for nearly three decades a Burlington Coat Factory — into a two-story, 55,000-square-foot ambulatory surgical center. The program holds six operating rooms and four procedure rooms, with EW Howell Construction Group as Construction Manager, CannonDesign as architect, and Cosentini Associates as MEP engineer.

Heleos VDC was engaged by the plumbing trade contractor, Lakeville Pace Mechanical, to model and coordinate the building's plumbing systems. Our job was to take the engineer's plumbing design and develop it into a coordinated, fabrication-ready model — clash-free against structure and the mechanical, fire-sprinkler, and electrical trades — before installation began. On an Article 28 surgery center built inside an old retail shell, that coordination is where budget and schedule are won or lost.

Aerial three-quarter view of the NYU Langone Patchogue Ambulatory Surgical Center model, showing the full building massing, the curtain-wall entrance facade, rooftop mechanical equipment, and adjacent structures.
Aerial cutaway view of the complete LOD 400 plumbing coordination model for the NYU Langone Patchogue Ambulatory Surgical Center, showing the full extent of blue sanitary, domestic water, and medical-gas piping distributed across both floors of the adaptive-reuse surgical facility.

The Challenge

Adaptive reuse means you inherit a building, not a blank slate. The existing roof structure and mechanical penthouse were removed, new side walls and a new roof went up, and fresh foundation work — underpinning, footings, and elevator pits — was added beneath a box that had been retail for half a century.

Then the program raised the bar. As an Article 28 ambulatory surgery center, the structure and MEP systems had to meet strict vibration criteria set by the authority having jurisdiction — tolerances a department store never had to satisfy.

That changes plumbing. Pipe routing, equipment placement, and especially hangers and supports all have to respect those criteria, not just hang from the nearest steel.

The bigger squeeze is overhead. Floor-to-floor heights are tight — 12 feet on the first floor, 9 feet on the second — so the ceiling plenum has very little room. Sanitary lines that need pitch, domestic water, storm leaders, ductwork, fire-sprinkler mains, electrical, and medical-gas piping all compete for the same few inches above the ceiling.

A surgical center also carries far denser plumbing than the retail use it replaced: scrub sinks, hub and floor drains, sterilizer and equipment drains, tempered water, and backflow protection that retail never required.

Five separate trade contractors share that plenum. Without a coordinated model, the conflicts surface in the field — as RFIs, change orders, and crews waiting on a wall.

Top-down plumbing plan view of the NYU Langone Patchogue Ambulatory Surgical Center, showing the full extent of LOD 400 blue domestic-water and sanitary piping across both floors of the adaptive-reuse surgical facility.
Close-up 3D BIM view of coordinated ductwork and pipe runs in a tight ceiling plenum at the NYU Langone Patchogue surgery center, with blue HVAC ducts and white domestic-water piping sharing a constrained overhead space.
Interior perspective of the LOD 400 coordination model showing blue MEP systems routed through the ceiling plenum of the NYU Langone Patchogue Ambulatory Surgical Center, including ductwork, piping, and structural elements in the tight floor-to-floor height.
Detailed BIM view of the mechanical room model at the NYU Langone Patchogue surgery center, showing coordinated blue piping, equipment connections, pumps, and support structure within the facility's MEP room.

The Plumbing Systems We Modeled

An Article 28 surgery center runs several plumbing systems at once, each with its own routing rules, slopes, and equipment. We modeled each one to LOD 350/400 — real pipe, real fittings, real valves — so the package that reached the field was buildable, not just diagrammatic.

Plumbing system scope reflects the contract documents Heleos VDC modeled and coordinated. Heleos VDC is not the engineer of record; equipment selection and system sizing are the design engineer's.

Our Workflow

  1. Translate the design into a fabrication model — we built the plumbing in Revit Fabrication directly from the CannonDesign and Cosentini contract drawings, modeling actual fabrication geometry (pipe, fittings, valves, and equipment) to LOD 350/400.
  2. Model real supports, sleeves, and offsets — hangers, supports, and penetrations were modeled with their true dimensions, so what cleared on screen cleared in the field, and so supports respected the project's vibration criteria.
  3. Run preliminary clash detection and remediate — we resolved plumbing conflicts against itself and the structure first, so the model reached the trade-coordination table already clean rather than full of obvious hits.
  4. Coordinate with the other MEP trades — we brought plumbing into a federated model with mechanical (Anron), fire sprinkler (Vanguard), and electrical (L.E.B.), and drove the conflicts to resolution before mobilization.
  5. Issue coordinated shop drawings — overhead and in-wall sections, elevations, and isometrics dimensioned off axis and grid lines, plus sleeve and box-out drawings, issued to the CM, design team, and ownership for review and approval.

Clash Detection & MEP Coordination

The plenum above an operating room is one of the most contested spaces in construction. Plumbing has to hold gravity pitch, ductwork needs its depth, sprinkler mains need coverage, and electrical and medical gas need their runs — all within nine feet floor-to-floor on the second level.

We federated every trade into a single coordination model and ran clash detection against structure and each other system. Each conflict was assigned, resolved, and re-checked — moving the fight off the job site and onto the screen, where a fix costs minutes instead of a change order.

Color tells the story. In the federated model, every trade carries its own color, so a conflict is obvious at a glance and easy to assign to the right contractor.

We also coordinated plumbing penetrations and supports with structure ahead of pours and framing, and placed valves, cleanouts, and access panels where a maintenance crew can actually reach them once the ceilings close.

What We Delivered

Tools Used

Results

By modeling the plumbing from the contract drawings and resolving clashes before trade coordination, the plumbing scope reached the field already vetted against structure and the other MEP trades — closing the gap between design intent and the building before installation began.

~60% — fewer in-field RFIs — a typical Heleos VDC outcome across projects run through a Heleos-led clash-detection cycle, shown for context; project-specific results vary by scope.

LOD 350/400

Fabrication-grade plumbing model built straight from the contract drawings.

55,000 SF

Coordinated across two stories of adaptive-reuse healthcare space.

Article 28

Healthcare-grade scope under strict vibration criteria.

Service & Location Summary

This Patchogue, New York project shows how Heleos VDC delivers fabrication-grade plumbing coordination, clash detection, and MEP coordination for Article 28 healthcare adaptive reuse on Long Island — turning the engineer's design into a coordinated, clash-free model so the trade contractor builds it right the first time. MODEL FIRST. BUILD ONCE.

Frequently Asked Questions

How did Heleos VDC develop the plumbing model for the NYU Langone Patchogue project?

Heleos VDC worked from the CannonDesign and Cosentini contract drawings — not a scan — building the plumbing in Revit Fabrication to LOD 350/400, modeling real supports and penetrations, running preliminary clash detection, and coordinating with the mechanical, fire-sprinkler, and electrical trades before installation began.

What makes plumbing coordination harder on an Article 28 surgery center?

As an Article 28 ambulatory surgery center, the structure and MEP systems had to meet strict vibration criteria set by the authority having jurisdiction, so pipe routing, equipment placement, and especially hangers and supports all had to respect those tolerances. Combined with tight floor-to-floor heights — 12 feet on the first floor and 9 feet on the second — there was little room above the ceiling for sanitary, domestic water, storm, and medical-gas-adjacent routing to share with ductwork, structure, and electrical.

What did Heleos VDC deliver for the NYU Langone Patchogue project?

An LOD 350/400 plumbing model in Revit Fabrication, preliminary clash detection and remediation, MEP trade coordination, overhead and in-wall shop drawings, hanger and support details, and sleeve and box-out penetration drawings — all issued for review and approval to the CM, design team, and ownership.

What was Heleos VDC's role on the project?

Heleos VDC delivered plumbing VDC for the project, engaged by the plumbing trade contractor, Lakeville Pace Mechanical. Heleos VDC is not the architect or engineer of record.

Project Location

196 East Main Street in Patchogue, NY — on Long Island's South Shore. NYU Langone Health is converting a long-vacant downtown retail building into a two-story, 55,000-square-foot ambulatory surgical center.

NYU Langone Patchogue Ambulatory Surgical Center — Patchogue, NY

Coordinates: 40.7654, -73.0151

Related Services

Explore More

Related Resources